CWASA to Boost Chattogram Water Supply by 50 Crore Litres Over Next Decade

Chattogram:Chattogram Water Supply and Sewerage Authority (CWASA) has unveiled plans to significantly enhance its water production capacity, aiming to increase daily output by an additional 50 crore litres over the next ten years. The initiative seeks to address the city's escalating demand for water.

According to Bangladesh Sangbad Sangstha, CWASA currently delivers 46-48 crore litres of water daily, falling short of the estimated demand of 70 crore litres. To bridge this gap, the agency has embarked on various short- and long-term projects to augment water supply and improve infrastructure.

Engineer Selim Mohammad Jane Alam, CWASA's Managing Director, stated that the organization has been supplying water to Chattogram since 1993, yet production levels have not kept up with the city's population growth. In the short term, CWASA plans to boost production at iron removal plants by four crore litres a day and expand the Karnaphuli Water Supply Project to add another 10 crore litres daily by 2031.

The Mohara Water Treatment Plant is also set for expansion, with plans to shift its intake point to the Karnaphuli River. A feasibility study is scheduled for December, aiming to add 30 crore litres of capacity. The Madunaghat Water Supply Project will similarly expand to 30 crore litres, with financial backing from the Korean Exim Bank.

In the long term, the Vandaljuri Water Supply Project will gain an additional 10 crore litres under a Public-Private Partnership (PPP) model, focusing on commercial use to meet industrial demand in southern Chattogram. Additionally, a project is underway to supply two crore litres of water daily to Patenga and surrounding areas via the Karnaphuli Tunnel.

CWASA plans to replace its aging supply pipelines, which are 35-40 years old, by 2030, and tenders for this are scheduled for March-April 2027. Areas outside the current network will gain coverage, with deep tube wells providing interim relief.

Engineer Selim assured that Chattogram would not face water-related issues until 2070 if these projects are completed within the next four to five years. While a proposal to source water from the Meghna River was shelved due to high costs, future projects will focus on the Karnaphuli River, ensuring sustainable extraction levels.

CWASA's first sewerage project in Halishahar is set to become operational by June 2027, with all city sewerage projects expected to be functional between 2035 and 2045. Challenges related to industrial pollution will be managed by the Department of Environment and other relevant ministries.

To address inadequate water supply in areas like South Khulshi and Kaibalya Dham Bishwa Colony, temporary measures through deep tube wells are in place, with plans for a direct supply system post-project completion. Revenue collection has improved, with monthly collections rising to Tk 28 crore, and efforts are underway to address billing issues and tackle illegal connections.