Rooppur Nuclear Plant Begins Supplying Electricity to National Grid

Ishwardi:Bangladesh's first nuclear power plant at Rooppur has initiated the supply of electricity to the national grid on a trial basis, marking a significant milestone. The plant's first unit began contributing 350 megawatts to the national grid during this initial phase.

According to Bangladesh Sangbad Sangstha, the power supply commenced at 316 pm in the presence of Science and Technology Minister Faqir Mahbub Anam. The Rooppur Nuclear Power Plant (RNPP) is part of the First Grid Connection (FGC) programme, under which electricity is scheduled to be supplied for 8 to 10 hours. The performance and stability of the plant's turbine, generator, and operating systems integrated with the national grid are being closely monitored.

The plant will be disconnected for technical tests after this initial phase, with plans to reconnect after about 28 hours for further evaluations. The ongoing tests aim to assess the plant's systems and ensure compatibility with the national grid. Approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) will be required to proceed to the next phase of trial operations if the results are satisfactory.

Present at the start of operations were Science and Technology Secretary Md Anwar Hossain, Bangladesh Atomic Energy Commission Chairman Dr. M Moinul Islam, BAERA Chairman Mahmudul Hasan, and other officials and engineers involved in the project. NPCBL Managing Director Dr. Zahedul Hasan emphasized that grid synchronisation tests are crucial for assessing the compatibility of the plant's electricity with the national grid.

The connection marks an important technical test rather than the start of commercial power generation, with power generation capacity to increase gradually following International Atomic Energy Agency guidelines and safety standards.