Dhaka:Construction of the Matarbari Port Development Project is advancing as planned, with approximately 3.6 million cubic meters of dredging completed, Shipping Minister Shaikh Rabiul Alam informed parliament today.
According to Bangladesh Sangbad Sangstha, the minister detailed that work on two of the three main packages of the Matarbari Port Development Project has commenced. This information was provided in response to a written query from treasury bench lawmaker Mohammad Mazharul Islam during a session of Jatiya Sangsad, presided over by Speaker Hafiz Uddin Ahmad, Bir Bikrom.
The minister explained the progress of Package-1, titled Civil Works for Port Construction, noting that a Notice to Proceed (NTP) was issued to the contractor, PT JV, on August 31, 2026, to start construction. Necessary equipment for land reclamation has already been delivered to the project site. Ongoing activities include building Geotube embankments, dredging, sand filling in Areas A and B, and carrying out CDM works.
Regarding Package-2A, which involves equipment, the Terminal Operating System (TOS), and security systems, the design and drawing preparations by the contractor, Mitsui E and S and Tec International Consortium of Japan, are nearing completion. A factory survey was conducted in Japan from April 4 to 11, 2026, to evaluate equipment manufacturing capabilities.
For Package-2B, concerning boats and the Vessel Traffic Management and Information System (VTMS), a meeting with a JICA delegation occurred at the Ministry of Shipping on September 2, 2026. The meeting resolved to solicit bidders' opinions on extending the tender validity period and bid security, as well as reducing the tender scope to expedite procurement.
The minister emphasized that the project, once completed, would accommodate large container vessels with a capacity of 8,200 TEUs at the port's jetty. Addressing concerns about potential delays, Shaikh Rabiul Alam assured that the port's activities are proceeding according to set procedures, with the seaport's establishment period extending until December 2029, indicating no delays in its establishment.