Medical &Health

RHD implements Taka 3,303.82cr projects in Rajshahi division

RAJSHAHI, The Roads and Highway Department (RHD) implemented various infrastructure development schemes involving around Taka 3,303.82 crore in last ten years till June last in Rajshahi division.

We have implemented diversified works like construction, reconstruction,

development and maintenance of roads, highways and bridges in Rajshahi,

Naogaon, Chapainawabgonj, Pabna, Sirajgonj and Natore districts, Additional

RHD Chief Engineer Habibur Rahman told BSS.

While being interview on Thursday he said a 51.626kilometer road from

Kansat to Bholahat via Rohanpur has been reconstructed and widened in

Chapainawabgonj as another 12.50kilometer Shaheed Monsur Ali road stretching

from Pipulbaria to Dhunat via Sonamukhi has been newly constructed in

Sirajgonj and Bogra districts.

With construction of 263meter Badalgachhi and Mohadevpur bridges, 24.58

kilometer road from Naogaon to Patnitala via Badalgachhi and 67.59kilometer

road from Patnitala to Rohanpur via Shapahar has been developed in Naogaon

and Chapainawabgonj districts, he said.

In addition to implementation of district road development project, a

47.47kilometer road from Godagari to Adda via Amnura, Nachole and Parbatipur

has been developed in Rajshahi and Naogaon districts, he added.

Rahman said: Currently, We are implementing seven mega infrastructure

development projects involving around Taka 2,136.37 crore. Implementation of

roads pavement widening project including the Natore town's main road from

Harishpur bypass crossing to Banbelghoria bypass crossing is underway.

Besides development work of 74km important regional highways to maintain

standard, and construction work of unfinished 19.5km NaogaonAtraiNatore

highway is progressing fast.

Construction of 14 bridges and culverts on different regional and national

highways is progressing under periodic maintenance programme.

Apart from this, repairing and maintenance work on 152.892km roads was

either completed or nearing completion under 13 packages of periodic

maintenance programme.

Roadside tree plantation activities are progressing successfully that will

ultimately help reduce carbon emission to a substantial level.

Rahman said that the implemented projects contribute enormously to raising

standard of living and the ongoing schemes will expedite the process upon

successful completion.